School
building panel CEO quits as audit details
waste
Report questions 'high' fees to
project management firms
Friday, March 10, 2006 BY DUNSTAN McNICHOL
Star-Ledger Staff
Change and charges of waste continue to
plague New Jersey's Schools Construction Corp.
The latest chapter played out yesterday
when the acting chief executive officer stepped down at the
agency's monthly meeting and the state auditor raised
questions about hundreds of millions of dollars in agency
expenditures.
The auditor's critical report on the
agency's first three years of operations added new detail to
allegations of mismanagement and waste that had been
outlined in earlier outside reviews of the
agency.
In particular, the auditor questioned
hundreds of millions of dollars in payments to 12 major
construction companies that were hired to oversee the
$6billion building program as project management
firms.
The firms have been paid $283million of
the $540million they are scheduled to collect under
contracts that award them fees worth 11 percent of the work
they oversee.
The auditor said those fees have been
inflated by various factors, and the 11 percent rate "seems
high" when compared with the 3 percent construction industry
standard for project managers. Even accounting for
additional tasks the state assigns to its PMFs, the auditor
says, the fee should be no more than 7 percent.
Applying that 7 percent rate to the PMF
contracts would reduce their costs by
$199million.
In addition, the auditor questioned
"mark-ups" of up to 192 percent for benefits, indirect costs
and profits that the private firms add onto the salary
charges they bill to the state.
While the SCC and its project management
firms pay comparable salaries, the audit said, "the
$182million staffing costs for the 14 PMF contracts reviewed
exceeded the comparable costs of the corporation's staff
(including benefits) by $59million -- or 48
percent."
In other areas, the auditor questioned
why the SCC replaced a construction cost limit of
$143million that was set by the Legislature with its own
$218-per-square-foot standard -- and further noted that even
that higher limit was largely ignored.
One school addition, for instance, cost
$621 per square foot to erect, the auditor noted.
The auditor also cited millions of
dollars wasted because of a "Fastrack" policy adopted to
speed the construction of new schools in the needy
communities. Under Fastrack, various project steps like land
acquisition, design and site development were undertaken
simultaneously to compress the time required for building a
school by 20 months.
"Although the Fastrack Approach may have
its theoretical benefits, its implementation on the
corporation's projects was not successful because there were
too many uncontrollable variables associated with the
initial phases of the project which resulted in additional
costs to the project," the auditor noted.
Ultimately, the Fastrack approach
resulted in wasted design and construction costs of
$65million to $105million, and led to the spending of
another $90million on projects that have been suspended or
canceled, the report notes.
In responses filed with the audit, SCC
officials said they have stopped using Fastrack. They also
said they are reviewing PMF payments and contract terms, and
will seek refunds for any payments deemed
inappropriate.
The auditor's review is the latest to
find deep problems in SCC management and
oversight.
Last year, after a Star-Ledger analysis
that found the SCC's building costs were 45 percent higher
than costs for other New Jersey school projects, the state
inspector general reviewed the agency and found management
problems that left the program open to "waste, fraud and
abuse of taxpayer dollars."
Overseeing the agency beginning Monday
will be Scott Weiner, a former state environmental
commissioner who was named special counsel to the schools
corporation by Gov. Jon Corzine a month ago. Weiner will be
the agency's fourth CEO in just over three years.
The current chief, Peter Maricondo, is
retiring about six months after he was named acting CEO upon
the resignation of his predecessor, Jack Spencer.
Spencer's departure last September capped
a turbulent year at the agency, in which officials announced
they had allocated the entire $6billion that lawmakers
authorized them to spend on a court-ordered makeover of
decrepit public schools, even though hundreds of school
projects remained unbuilt.
Maricondo was brought in to be the SCC's
first chief financial officer last year as part of a
sweeping overhaul by former Gov. Richard Codey. He is
credited with setting realistic budgets and accounting
standards for the 100 projects still in the
works.
"We made some good progress," he said
yesterday. "I just feel that this point in time is an
appropriate time to retire."
Since his appointment to the board in
February, Weiner has been working on a report scheduled to
be delivered to Corzine next Wednesday on options for
changing operations at the corporation.
Weiner said the agency hopes to complete
an ongoing search for a permanent chief executive within
several months.
Dunstan McNichol covers state government issues. He may
be reached at dmcnichol@starledger.com or (609) 989-0341.
© 2006 The Star-Ledger. Used by NJ.com with
permission.
|