Work at school site won't stop

Dozens of people promise to help P'burg School District fight for new high school.
Friday, August 05, 2005 • By PRECIOUS PETTY • The Express-Times

PHILLIPSBURG -- The first battle in the war to get a new Phillipsburg High School built is to make sure preliminary work already under way at the project site continues, district officials told the public Thursday at a special board of education meeting.

Superintendent Gordon Pethick said he's learned the state agency overseeing the work didn't set aside any money for it, a fact which could further encumber the beleaguered high school project.

"If the site work package didn't continue, we'd have some real problems," he said.

Last week, the same state agency announced it would not pay for the second -- and much more expensive -- phase of the project: construction of a roughly $90 million, 379,601-square-foot structure to serve 2,000 students.

The school board called Thursday's meeting to give the community an update on the high school project's status. Dozens of people attended the hour-and-a-half long meeting, many of them representatives from municipalities and school districts that feed students to the high school.

All of them promised to help the Phillipsburg School District in its fight for a new high school.

"We're not going to stand behind Phillipsburg; we're going to stand next to it," Lopatcong Township Board of Education President Ernie Gallant said.

Former Phillipsburg School Board member Irene Weller reminded the school board and area residents to stay focused in their fight.

"What has happened has happened," she said. "What happens from here on in is definitely up to us. Now the only thing that's going to help is positive, aggressive action."

Pethick said he's heard from Sen. Leonard Lance, R-Hunterdon/Warren, and other legislators, who vowed to do battle for the high school.

So far, workers are 65 days and $2.5 million into the 210-day, $7.5 million-job, which is phase one of the overall project, Pethick said. If the job is stopped now, all of the work completed would be lost, he said.

Preliminary work at the site in Lopatcong Township includes the construction of seven athletic fields, parking lots and a three-quarter-mile entrance drive from Belvidere Road. The access road must be completed before the school can be built.

"Once something like this has started, it would be a travesty to stop it," said school board President Rod L. Pianelli.

Richard Shapiro, an attorney who specializes in education law, told those at the meeting to lobby their legislators, urging them to find out how much it will cost to pay for Phillipsburg's project and others that were cut from the state's list last week.

In the meantime, Shapiro plans to file a petition with the New Jersey Supreme Court on behalf of Phillipsburg -- and several other school districts whose construction projects were nixed by the state -- asking it to force New Jersey to pay for the new high school.

Phillipsburg is one of New Jersey's 31 Abbott, or most needy, districts, a status that requires the state to cover all of its Department of Education-approved construction costs. Therefore, the district expected the New Jersey Schools Construction Corp. -- a state agency formed by former Gov. James McGreevey -- to pay for Phillipsburg's new high school.

However, Phillipsburg was left in the lurch last week when the SCC announced the high school had been cut from a list of projects the agency plans to complete with the last $1.4 billion of a special fund. The fund was created in 2000 in light of the landmark Abbott v. Burke rulings.

Hundreds of other Abbott district construction projects also were nixed, including Phillipsburg's plan to renovate Andover-Morris Elementary School for an estimated $13 million. Only 59 of an anticipated 350 projects are still moving forward.


© 2005 The Express-Times. Used with permission.

Return to Articles page