School builders ask time to 'get act together'

Pending projects on hold at least 6 months, agency tells justices
Tuesday, November 08, 2005 • BY DUNSTAN McNICHOL • Star-Ledger Staff

New Jersey's troubled Schools Construction Corp. needs at least six months to "get its house in order" before it can return to work on hundreds of school projects that were shelved last summer, a lawyer for the agency told the state Supreme Court yesterday.

Attorneys for students in the 31 communities where the SCC is under court order to improve hundreds of decrepit schools appeared before the Supreme Court yesterday, seeking an order that would require the Department of Education to request additional funds from lawmakers within 15 days.

"There's an immediate need," said David Sciarra, lead attorney for the students. "We are asking for some time frame to get it done."

Nancy Kaplen, attorney for the SCC and the Education Department, said the state will not be in position to seek or spend any additional funds from lawmakers until the middle of next year, at the earliest.

"You need to give the agency a little bit of time to get its act together," Kaplen said. "They're moving along, but they have so many balls in the air."

The hearing was the latest in the long-running Abbott vs. Burke case over public school funding in New Jersey's poorest communities. In a landmark 1998 ruling, the court ordered a series of sweeping reforms, including the repair or renovation of hundreds of school buildings that were deemed obsolete and overcrowded.

Since then, the state has exhausted the first $6 billion lawmakers allocated to the construction effort.

With that money, Kaplen said, the state has repaired 350 schools, built 11 schools and started work on 63 more new school buildings. In July, agency officials suspended work on about 200 more school projects, citing a lack of funds.

Sciarra and the Education Law Center, the nonprofit agency that has pushed the Abbott case, want the state to calculate the cost of completing those projects in order to be able to petition the Legislature for additional funding.

But Kaplen said compiling those estimates would divert the SCC's staff from the two key tasks of completing the 63 schools under construction and retooling the agency's internal operations.

"I think there's a limitation to how much multi-tasking it can take on," Kaplen said.

Kaplen said it will take at least two years to finish building the schools currently in the works. She said the agency likely will be able to identify a new round of projects it can begin within six months.

The SCC has been reorganizing since April, when a scathing state inspector general's report concluded that the agency was vulnerable to waste and abuse of its funds because it lacked basic financial management tools.

That report was prompted by a Star-Ledger analysis that found that cost overruns and costly professional contracts led the first six schools built by the SCC to cost, on average, 45 percent more than schools built by local school districts at the same time.

Since those reports, the SCC has replaced its top management and rewritten its contracts with architects and other professionals to save the state money.

At least three of the court's seven justices expressed concern that schoolchildren will be harmed by any continued delay in the SCC's reorganization and contracting.

"What do you say to the children in Elizabeth?" Justice Barry T. Albin asked Kaplen, referring to one of the communities included in the court's construction order. "'You're going to learn in cramped quarters; you're going to have lunch in the hallways,' and all these other details that have been presented to us?"

The court declined to issue an immediate opinion after the 45-minute presentations.


Dunstan McNichol covers state government issues. He may be reached at dmcnichol@starled ger.com or (609) 989-0341.
© 2005 The Star-Ledger. Used by NJ.com with permission.

Return to Articles page